Wasa (Vasa) – Hull construction from 20 November 2020

Wasa (Vasa) Hull construction 

25 January 2021  Hull completed 

 

19 January 2021  Hull completed for’ard with access for bowsprit

18 January 2021  Port side planks 25, 26, 27, 28 tapered, cut, bent, fitted, glued, trimmed aft

18 January 2021  Port side planks 23, 24 tapered at bow, cut, bent, fitted, glued, trimmed aft

18 January 2021  Port side plank 22 tapered at bow, cut, bent, fitted, glued, trimmed aft

17 January 2021  Port side plank 21 tapered at both ends, cut, bent, fitted, glued

17 January 2021  Port side plank 20 tapered at both ends, cut, bent, fitted, glued

17 January 2021  Port side plank 19 tapered at both ends, cut, bent, fitted, glued

17 January 2021  Port side plank 18 tapered at both ends, cut, bent, fitted, glued

16 January 2021  Port side plank 17 tapered at bow, cut, bent, fitted, trimmed, glued

16 January 2021  Port side plank 16 tapered at bow, cut, bent, fitted, trimmed, glued

16 January 2021  Port side plank 15 tapered at bow, cut, bent, fitted, trimmed, glued

16 January 2021  Port side plank 14 tapered at bow, cut, bent, fitted, trimmed, glued

16 January 2021  Port side plank 13 tapered at bow, cut, bent, fitted, trimmed, glued

16 January 2021  Port side plank 12 tapered at bow, cut, bent, fitted, trimmed, glued

16 January 2021  Port side plank 11 cut, bent, fitted, trimmed, glued

15 January 2021  Port side plank 10 cut, bent, fitted, trimmed, glued

15 January 2021  Port side plank 9 cut, bent, fitted, trimmed, glued

15 January 2021  Port side plank 8 cut, bent, fitted, trimmed, glued

14 January 2021  Port side plank 7 cut, trimmed, glued

14 January 2021  Port side plank 6 cut, trimmed, glued

14 January 2021  Port side plank 5 cut, trimmed, glued

14 January 2021  Port side plank 4 cut, trimmed, glued

13 January 2021  Port side plank 3 cut, trimmed, glued  

11 January 2021  Port side plank 2 cut, trimmed, glued 

11 January 2021  Port side plank 1 cut, trimmed, glued 

10 January 2021  Starboard side planking completed 

10 January 2021  Starboard side plank 28 (stern), 29 (bow) cut, thinned, tapered at both ends, squared aft & glued

   

10 January 2021  Starboard side plank 27 cut, thinned, tapered at both ends, squared aft, pinned & glued

10 January 2021  Starboard side plank 26 cut, tapered at both ends, squared aft, pinned & glued

10 January 2021  Starboard side plank 25 cut, tapered at both ends, pinned & glued

9 January 2021  Starboard side plank 24 cut, tapered at both ends, pinned & glued

9 January 2021  Starboard side plank 23 cut, tapered at both ends, pinned & glued

9 January 2021  Starboard side plank 22 cut, tapered at both ends, pinned & glued

9 January 2021  Starboard side plank 21 cut, tapered at both ends, pinned & glued

9 January 2021  Starboard side plank 20 cut, tapered at fore end, pinned & glued, after end to be trimmed

9 January 2021  Starboard side plank 19 cut, tapered at fore end, pinned & glued, after end to be trimmed

8 January 2021  Starboard side plank 18 cut, tapered at fore end, pinned & glued, after end to be trimmed

8 January 2021  Starboard side plank 17 cut, tapered at fore end, pinned & glued, after end to be trimmed

8 January 2021  Starboard side plank 16 cut, tapered at fore end, pinned & glued, after end to be trimmed

8 January 2021  Starboard side plank 15 cut, tapered at fore end, pinned & glued, after end to be trimmed

8 January 2021  Starboard side plank 14 cut, tapered at fore end, pinned & glued, after end to be trimmed

8 January 2021  Starboard side plank 13 cut, tapered at fore end, pinned & glued, after end to be trimmed

8 January 2021  Starboard side plank 12 cut, tapered at fore end, pinned & glued, after end to be trimmed

7 January 2021  Starboard side plank 11 cut, fitted, pinned & glued, after end trimmed

7 January 2021  Starboard side plank 10 cut, fitted, pinned & glued, after end trimmed

7 January 2021  Starboard side plank 9 cut, fitted, pinned & glued, after end trimmed

7 January 2021  Starboard side plank 8 cut, fitted, pinned & glued, after end trimmed

7 January 2021  Starboard side plank 7 cut, fitted, pinned & glued. After ends of planks trimmed

6 January 2021  After infills cut, fitted, glued

6 January 2021  Starboard side plank 6 cut, fitted, pinned & glued

6 January 2021  Starboard side plank 5 cut, fitted, pinned & glued

5 January 2021  Starboard side plank 4 cut, fitted, pinned & glued

5 January 2021  Starboard side plank 3 cut, fitted, pinned & glued

4 January 2021  Starboard side plank 2 cut, fitted, pinned & glued

3 January 2021  Starboard side plank 1 cut, fitted, glued

3 January 2021  Transom planking trimmed, smoothed and infills cut, shaped, fitted, glued

2 January 2021  Transom planking fitted, glued

2 January 2021  Aft framework revised

1 January 2021  Aft framework 155, 152 and 6 x 113

1 January 2021  Focs’l bulkhead fitted, glued

31 December 2020  Handrail terminals fitted and glued, port and starboard

31 December 2020 Poop deck handrails fitted, glued to frame ends

29 December 2020 Quarterdeck handrails for’rd end fitted, glued

27 December 2020 For’ard deck and well deck handrails fitted, glued

26 December 2020 Frame ends well deck port and starboard, port for’ard & handrails for’ard, well deck

25 December 2020  Starboard hull upper section for’ard fitted with frame ends

24 December 2020  Deck edges port and starboard cut and glued

23 December 2020  Model stand prepared, assembled

 

23 December 2020  Hull sides packed, glued

18 December 2020  Starboard upper hull side fitted, glued

18 December 2020  Port upper hull side fitted, glued

18 December 2020  focs’l deck bulkhead, doors, and frame fitted

16 December 2020  Main deck bulkhead, door, combing and ladders

16 December 2020  Quarterdeck deck bulkhead, door, combing and ladder

16 December 2020  Poop deck wall, door, combing and fittings

12 December 2020  Primary varnish on decks and gratings

10 December 2020  After castle parts 32, 33 and inner after castle parts 18, 19, 20, 23, 29, 31, 36

 

8 December 2020  Planking on focs’l deck completed

7 December 2020  Main deck combing around gratings completed

7 December 2020  Quarterdeck and poopdeck deck planking completed

6 December 2020  Cabin deck planking completed

6 December 2020  Main deck planking completed

6 December 2020  Central section of main deck planked

4 December 2020  Grating supports added to main deck

4 December 2020  Gratings prepared

3 December 2020  Quarterdeck structure glued onto quarterdeck

3 December 2020  Quarterdeck structure assembled

 

3 December 2020  Poop deck structure assembled aft

1 December 2020  Stretchers cut, fitted and glued to frames 1 to 3, deck fitted, glued. Main decks port and starboard dry fitted

30 November 2020  Stretchers cut, fitted and glued to frames 13 to 3

30 November 2020  Frames 8 to 13  fitted to keel with frame spacers and mast supports

29 November 2020  Frames 1 to 7  fitted to keel with frame spacers and mast supports

27 November 2020  Frames 13 down to 4 marked on main deck former

27 November 2020  For’ard frame 13 and parts 16 x 2 and 17 x 2 dry assembled

   

24 November 2020  After frame 1 and additions dry assembled

   

23 November 2020 Keel assembled, glued

20 November 2020 Main frames 1 to 13 cut out

20 November 2020 Keel cut, bow and stern assembled and reinforcements all dry assembled